USAO Secure Processing Room

Oct 1, 2021

This project constructed a new Secure Processing Room (SPR) on the third floor of the EM Dirksen Federal Courthouse in accordance with the USAO Chicago, II SPR Master Specifications. Architectural work included new RF shielded partitions, ceiling and flooring, new secure doors, frames, and hardware. Electrical work included an isolated ground service to the space and new outlets and lights. HVAC work included the installation of a new independent HVAC system with grounding or dielectrics for all piping running through the space. Due to the secure nature of this project, no photos of the finished space were permitted.

PROJECT TYPE

Design-Bid-Build

OWNER

General Services Administration

LOCATION

EM Dirksen Federal Courthouse, 219 S. Dearborn St, Chicago, IL

CONTRACT VALUE

$360K